Progress photos below by date in construction area - When finished viewing - Esc then Back key

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Capital Facilities Project Information 


Legal Notice

   

Plans/Drawings
Marlboro-Plan Down 
Marlboro-Plan Up 
 
Scope of Work
Marlboro

Milton

Middle Hope

 

News Letters
December 2002

November  2002
February   2002
November   2001
October     2001
June          2001

Information
Why Now ?
Voting Information
Understanding the Cost

 

Return To Home

While you're visiting
MVLA
NYPL
The Exploratorium
Lifelines
PPLD
Funbrain

 

 
Marlboro Elementary School looking East towards the Hudson River

 

 

Marlboro Elementary School looking West towards Route 9-W

Project Information

Elementary School Project Update

We are pleased to be moving forward on all three phases of the improvement plan to address issues at Milton, Middle Hope, and Marlboro elementary schools. As you may recall, this $33 million project was approved by voters on December 17, 2002.

 

Here is a report on our progress.

Hope

 

Phase 1 — This phase encompasses the construction of the new kindergarten addition and new mechanical/boiler room at Marlboro Elementary School.

bullet Bids are planned to be received on March 11, 2004 and awarded soon after
bullet Construction is scheduled to begin on or about April 1, 2004
bullet Completion is slated for Fall 2004

 

Phase 2 — This phase includes construction of a new grade 3-5 addition and renovations to the existing building at Marlboro Elementary School.

bullet Comprehensive construction plans were submitted to the State Education Department (SED) in November 2003
bullet We anticipate this review will be completed by the end of April 2004
bullet We anticipate construction documents will go out to bid in May 2004*
bullet We anticipate construction will begin in Summer 2004*

*     Timeframe is contingent upon SED review schedule